Our Liberty 45 on the Northern Beaches, Sydney
Liberty Verve
Thursday, 31 March 2016
Frames taking shape
Sunday, 6 March 2016
Frames arrived, should take shape this week....
Hope the weather holds up for two more weeks!
Monday, 29 February 2016
Storm water and drainage installed
Another two good days work installing stormwater, waste and other drainage. Nice work....
Tuesday, 23 February 2016
Drop edge beam
Monday, 22 February 2016
Slab down, looks HUGE!
Waffle pod down, pour day tomorrow
Big day tomorrow, prep work complete.....
Saturday, 30 January 2016
Pre slab
Finishing touches before the slab is put down.